General
Our report and any quotation provided remains valid for a period of 3 calendar months from the date of issue. Our report should not be relied upon after this period.
All information sheets, specifications, and conditions of contract are taken as agreed to by the client should Abbott Property Care Ltd be allowed to commence work on site.
Although every effort will be made to start and complete an installation or treatments within agreed schedules, Abbott Property Care Ltd cannot accept responsibility for losses incurred due to delays.
There will be mess associated with the works and although we will sweep through the treatment rooms, a certain amount will undoubtedly remain. Dust may settle for several days following treatment. Further cleaning costs are not included in our quotation. A ‘builder’s clean’ is offered by cleaning companies and should be considered following remedial work involving re-plastering.
No responsibility can be taken by Abbott Property Care Ltd for any damage to electrical wiring or plumbing piping, valves, etc. (including gas) caused during the work.
Where the property to be treated is in a Conservation Area or is Statutorily Listed, the client should inform the relevant authority and obtain their permission before treatment commences. Abbott Property Care Ltd will assume that such permission has been obtained if instructed to proceed.
Good ventilation should be maintained for a period of 48 hours following all remedial treatments.
Following the completion of a damp proof course installation the drying out period is generally 9 – 12 months for a wall of double brick thickness. Drying out is however subject to ventilation and weather conditions.
Party Walls
Where a party wall is to be treated the client should obtain written permission from the neighbouring property owner(s)/occupant(s) involved under the terms of The Party Wall Act 1996. Abbott Property Care Ltd will assume permission has been obtained if instructed to proceed with such works.
Where the thickness of a party wall exceeds a single brick thickness, treatment will be limited to single brick thickness. Any bridging of dampness from the part of wall not treated treatment will not be covered by our guarantee. Should treatment be required to a party wall thickness exceeding single brick thickness, Abbott Property Care Ltd must be notified in writing and reserves the right to refuse to carry out such work.
Client’s preparation work
All treatment areas must be cleared of carpets, furniture and electrical goods prior to treatment taking place. No responsibility can be accepted by Abbott Property Care Ltd for damage to any items remaining in treatment rooms during the course of the work. No allowance is made in our quotations for the removal or refitting of any kitchen units, wall tiling or appliances.
Skirting boards
We will refit skirting boards free of charge if they are in good condition. If skirting boards are not suitable for refitting (due to decay, woodworm or damage during removal), we can provide a quotation to fit new ones under separate contract. New skirting boards should not be fitted until the plaster has dried (around 4 weeks).
If the property has tiled skirtings then the client must make separate arrangements to remove the tiles before work is commenced and make good afterwards.
Radiators, plumbing fitments and fitted units
Where applicable, radiators, plumbing fitments and fitted units should be removed prior to commencement of works.
Redecoration
Normal re-decoration cannot be carried out for a minimum of six months following damp proof course installation. As a temporary measure, a single coat of water-based matt emulsion paint can be applied after 3 – 4 weeks.
Removing plaster and re-plastering work is likely to cause damage to the decoration on adjacent wall and ceiling areas. Redecoration following re-plastering work may therefore be significantly more extensive than simply the immediate area re-plastered.
Before applying any decoration, 2 coats of ‘Zinsser BIN’ stain block should be applied across all joins to a width of 150mm where the new plaster meets the original plaster. ‘Zinsser BIN’ should also be applied where the new plaster meets skirting boards and door frames, essentially creating a border or frame around the new plaster.